Clearing, Desilting and Declogging of Waterways at San Agustin, Cuidad de Hizon–Villa Del Sol
Status as of August 30, 2026
Project at a Glance
Financial Overview
Budget and contract amounts
APP Estimated Budget
₱5,000,000.00
Approved Budget for Contract (ABC)
₱5,000,000.00
Winning Bid Amount
Not available
Contract Amount
₱4,984,842.75
99.70% of ABC
Difference from ABC
₱15,157.25
0.30% difference
Timeline
Project timeline
May 19, 2026
Award date
May 25, 2026
Contract effectivity
August 1, 2026
Contract end
Reference
Project Identifiers
Provenance
Evidence & official sources
Official documents used to establish project facts.
APP
Official source · Document verified
Establishes: project name, year, implementing office, location text, barangay, estimated budget, funding source, procurement mode, app code
Source identifier
2026-00801
Document date
Not available
ITB
Official source · Document verified
Establishes: project name, primary procurement id, approved budget abc, funding source
Source identifier
2026-03-00587
Document date
Not available
Notice OF Award
Official source · Document verified
Establishes: primary procurement id, contract number, contract amount, contractor, award date, contract effectivity date, contract end date, procurement mode, funding source
Source identifier
2026-03-00587
Document date
Not available