Awarded
Construction of Oval, (Phase 2) at the City Civic Center, San Isidro
San Isidro2025Park RecreationInfrastructure Capital
Status as of August 30, 2026
Project at a Glance
Financial Overview
Budget and contract amounts
Approved Budget (ABC)
₱9,500,000.00
Winning Bid Amount
₱9,487,929.03
99.87% of ABC
Contract Amount
Not available
Timeline
Project timeline
Award and contract milestone dates are not yet established in the published project record.
Reference
Project Identifiers
Provenance
Evidence & official sources
Official documents used to establish project facts.
BID Results
Official source · Document verified
Establishes: project name, primary procurement id, approved budget abc, contractor, winning bid amount, location text
Source identifier
2025-02-00572
Document date
April 8, 2025
Procurement Monitoring Report
Official source · Document verified
Establishes: funding source, procurement mode
Source identifier
2025-02-00572
Document date
Not available