Improvement/Construction of Road at San Pedro
Status as of September 12, 2026
Project at a Glance
Financial Overview
Budget and contract amounts
APP Estimated Budget
Not available
Approved Budget for Contract (ABC)
₱3,000,000.00
Winning Bid Amount
Not available
Contract Amount
₱2,991,759.51
99.73% of ABC
Difference from ABC
₱8,240.49
0.27% difference
Timeline
Project timeline
October 31, 2024
Award date
November 5, 2024
Contract effectivity
January 12, 2025
Contract end
Utilization
Project Cost & Utilization
Source-reported, year-to-date figures for a bounded subset of published projects — not proof of cash payment, disbursement, or completion. View the full Project Cost & Utilization statistics.
Latest observation — 2024 Q4
Cost incurred to date
99.73%
2,991,759.51 of 3,000,000 total cost
Derived from the source-reported cost figures.
Physical completion
99.73%
Source-reported physical completion
Source-reported status
Completed
Observation history
Project utilization history
Compare the verified year-to-date figures published for this project across reporting periods.
Each observation is year-to-date, so the figures should be compared across periods rather than added together.
2024 Q2
Cost incurred0%
Physical completion0%
Source-reported statusOn going
Official source2024 Q3
Cost incurred0%
Physical completion0%
Source-reported statusNo notice to proceed
Official source2024 Q4Latest
Cost incurred99.73%
Physical completion99.73%
Source-reported statusCompleted
Official source
These are year-to-date figures from the official source, not proof of cash payment or disbursement. Currency is not stated in the source; amounts are shown as plain numbers. Coverage is limited to a bounded subset of published projects.
Reference
Project Identifiers
Provenance
Evidence & official sources
Official documents used to establish project facts.
NTA Utilization Report
Official source · Document verified
Establishes: project name, location text
Source identifier
nta-2024-q3
Document date
Not available
NTA Utilization Report
Official source · Document verified
Establishes: project name, location text
Source identifier
nta-2024-q2
Document date
Not available
NTA Utilization Report
Official source · Document verified
Establishes: project name, location text
Source identifier
nta-2024-q4
Document date
Not available
Notice OF Award
Official source · Document verified
Establishes: philgeps reference, primary procurement id, approved budget abc, contract amount, contractor, procurement mode, award date, contract number, contract effectivity date, contract end date
Source identifier
2024-08-01629
Document date
October 31, 2024