Improvement/Construction of Road at Malino

Malino2024RoadInfrastructure Capital

Status as of August 30, 2026

Project at a Glance

Barangay
Malino
Contractor
Ann Reyrick Construction
Funding source
Government of the Philippines (GOP) / Budget for the Contract Approved by the Sanggunian
Procurement mode
Public Bidding

Financial Overview

Budget and contract amounts

Approved Budget (ABC)

₱3,000,000.00

Winning Bid Amount

₱2,991,338.25

99.71% of ABC

Contract Amount

₱2,991,338.25

99.71% of ABC

Difference from ABC

₱8,661.75

0.29% difference

Timeline

Project timeline

  1. May 2, 2024

    Award date

  2. May 8, 2024

    Contract effectivity

  3. July 30, 2024

    Contract end

Utilization

Project Cost & Utilization

Source-reported, year-to-date figures for a bounded subset of published projects — not proof of cash payment, disbursement, or completion. View the full Project Cost & Utilization statistics.

Latest observation — 2024 Q4

Cost incurred to date

99.71%

2,991,338.25 of 3,000,000 total cost

Derived from the source-reported cost figures.

Physical completion

99.71%

Source-reported physical completion

Source-reported status

Completed

Observation history

Project utilization history

Compare the verified year-to-date figures published for this project across reporting periods.

Each observation is year-to-date, so the figures should be compared across periods rather than added together.

  1. 2024 Q2

    Cost incurred99.71%

    Physical completion99.71%

    Source-reported statusCompleted

    Official source
  2. 2024 Q3

    Cost incurred99.71%

    Physical completion99.71%

    Source-reported statusCompleted

    Official source
  3. 2024 Q4Latest

    Cost incurred99.71%

    Physical completion99.71%

    Source-reported statusCompleted

    Official source

These are year-to-date figures from the official source, not proof of cash payment or disbursement. Currency is not stated in the source; amounts are shown as plain numbers. Coverage is limited to a bounded subset of published projects.

Reference

Project Identifiers

Bid Reference
2024-02-00481
Contract Number
2024-04-01193
PhilGEPS Reference
10662134

Provenance

Evidence & official sources

Official documents used to establish project facts.

  1. Notice OF Award

    Official source · Document verified

    Establishes: philgeps reference, contract number, approved budget abc, contract amount, contractor, award date, contract effectivity date, contract end date

    Source identifier

    2024-02-00481

    Document date

    May 2, 2024

  2. BID Results

    Official source · Document verified

    Establishes: approved budget abc, contractor, winning bid amount

    Source identifier

    2024-02-00481

    Document date

    April 16, 2024