Awarded
Construction of Lined Canal at Del Pilar
Del Pilar2024DrainageInfrastructure Capital
Status as of August 30, 2026
Project at a Glance
Financial Overview
Budget and contract amounts
Approved Budget (ABC)
₱2,500,000.00
Winning Bid Amount
₱2,492,057.64
99.68% of ABC
Contract Amount
Not available
Timeline
Project timeline
Award and contract milestone dates are not yet established in the published project record.
Reference
Project Identifiers
Provenance
Evidence & official sources
Official documents used to establish project facts.
BID Results
Official source · Document verified
Establishes: project name, primary procurement id, approved budget abc, contractor, winning bid amount, location text
Source identifier
2024-03-00569
Document date
April 30, 2024