Improvement/Construction of Road at Alasas
Status as of August 30, 2026
Project at a Glance
Financial Overview
Budget and contract amounts
APP Estimated Budget
Not available
Approved Budget for Contract (ABC)
₱3,000,000.00
Winning Bid Amount
₱2,991,734.56
99.72% of ABC
Contract Amount
₱2,991,734.56
99.72% of ABC
Difference from ABC
₱8,265.44
0.28% difference
Timeline
Project timeline
April 1, 2024
Award date
April 2, 2024
Contract effectivity
August 9, 2024
Contract end
Utilization
Project Cost & Utilization
Source-reported, year-to-date figures for a bounded subset of published projects — not proof of cash payment, disbursement, or completion. View the full Project Cost & Utilization statistics.
Latest observation — 2025 Q3
Cost incurred to date
99.68%
2,990,493.52 of 3,000,000 total cost
Derived from the source-reported cost figures.
Physical completion
99.68%
Source-reported physical completion
Source-reported status
Completed
Observation history
Project utilization history
Compare the verified year-to-date figures published for this project across reporting periods.
Each observation is year-to-date, so the figures should be compared across periods rather than added together.
2024
Q2
Cost incurred99.72%
Physical completion99.72%
Source-reported statusCompleted
Official sourceQ3
Cost incurred99.72%
Physical completion99.72%
Source-reported statusCompleted
Official sourceQ4
Cost incurred99.72%
Physical completion99.72%
Source-reported statusCompleted
Official source
2025
Q1
Cost incurred99.68%
Physical completion99.68%
Source-reported statusCompleted
Official sourceQ2
Cost incurred99.68%
Physical completion99.68%
Source-reported statusCompleted
Official sourceQ3Latest
Cost incurred99.68%
Physical completion99.68%
Source-reported statusCompleted
Official source
These are year-to-date figures from the official source, not proof of cash payment or disbursement. Currency is not stated in the source; amounts are shown as plain numbers. Coverage is limited to a bounded subset of published projects.
Reference
Project Identifiers
Provenance
Evidence & official sources
Official documents used to establish project facts.
Notice OF Award
Official source · Document verified
Establishes: philgeps reference, contract number, approved budget abc, contract amount, contractor, award date, contract effectivity date, contract end date
Source identifier
2024-01-00310
Document date
April 1, 2024
BID Results
Official source · Document verified
Establishes: contractor, winning bid amount
Source identifier
2024-01-00310
Document date
March 14, 2024
NTA Utilization Report
Official source · Document verified
Establishes: project name, location text
Source identifier
nta-2025-q3
Document date
Not available
NTA Utilization Report
Official source · Document verified
Establishes: project name, location text
Source identifier
nta-2025-q1
Document date
Not available
NTA Utilization Report
Official source · Document verified
Establishes: project name, location text
Source identifier
nta-2025-q2
Document date
Not available