Awarded
Improvement/Construction of Lined Canal at Quiwa Road, Del Pilar
Del Pilar2023DrainageInfrastructure Capital
Status as of August 30, 2026
Project at a Glance
Financial Overview
Budget and contract amounts
Approved Budget (ABC)
₱2,000,000.00
Winning Bid Amount
₱1,989,054.87
99.45% of ABC
Contract Amount
Not available
Timeline
Project timeline
Award and contract milestone dates are not yet established in the published project record.
Reference
Project Identifiers
Provenance
Evidence & official sources
Official documents used to establish project facts.
BID Results
Official source · Document verified
Establishes: project name, primary procurement id, approved budget abc, contractor, winning bid amount, location text
Source identifier
2023-02-00331
Document date
March 28, 2023
Procurement Monitoring Report
Official source · Document verified
Establishes: funding source, procurement mode
Source identifier
2023-02-00331
Document date
Not available