Site Development of the Civic Center (Logistic and Support Area) Phase I at Alasas

Alasas2022Other InfrastructureInfrastructure Capital

Status as of August 30, 2026

Project at a Glance

Barangay
Alasas
Contractor
Cholo Construction and Trading
Funding source
Not available
Procurement mode
Not available

Financial Overview

Budget and contract amounts

Approved Budget (ABC)

₱5,000,000.00

Winning Bid Amount

₱4,989,464.96

99.79% of ABC

Contract Amount

Not available

Timeline

Project timeline

Award and contract milestone dates are not yet established in the published project record.

Reference

Project Identifiers

Bid Reference
2022-02-00358

Provenance

Evidence & official sources

Official documents used to establish project facts.

  1. BID Results

    Official source · Document verified

    Establishes: project name, primary procurement id, approved budget abc, contractor, winning bid amount, location text

    Source identifier

    2022-02-00358

    Document date

    March 15, 2022