Awarded
Construction/Improvement of Lined Canal Phase 2 at Alasas
Alasas2022DrainageInfrastructure Capital
Status as of August 30, 2026
Project at a Glance
Financial Overview
Budget and contract amounts
Approved Budget (ABC)
₱570,000.00
Winning Bid Amount
₱563,721.06
98.90% of ABC
Contract Amount
Not available
Timeline
Project timeline
Award and contract milestone dates are not yet established in the published project record.
Reference
Project Identifiers
Provenance
Evidence & official sources
Official documents used to establish project facts.
BID Results
Official source · Document verified
Establishes: project name, primary procurement id, approved budget abc, contractor, winning bid amount, location text
Source identifier
2022-02-00387
Document date
March 3, 2022