Awarded
Construction/Completion of Four(4)-Storey, Twenty (20) Classroom Building 1 at San Fernando Elementary School
Barangay not attributed2022BuildingInfrastructure Capital
Status as of August 30, 2026
Project at a Glance
Financial Overview
Budget and contract amounts
Approved Budget (ABC)
₱20,000,000.00
Winning Bid Amount
₱19,986,970.67
99.93% of ABC
Contract Amount
Not available
Timeline
Project timeline
Award and contract milestone dates are not yet established in the published project record.
Reference
Project Identifiers
Provenance
Evidence & official sources
Official documents used to establish project facts.
BID Results
Official source · Document verified
Establishes: project name, primary procurement id, approved budget abc, contractor, winning bid amount, location text
Source identifier
2022-02-00227
Document date
March 2, 2022